After visiting with them and showing them the radar, the construction crew was a little worried about the incoming storms, but like all of us, there was nothing they could do. We laughed, thinking they had just built a big wadding pond. I asked about the timeline, and Chuck Williams from KLJ sent me the following best estimate :
Construction mobilization July 5
Traffic control July 5-6
Construction begins July 6
Close north side of Main St July 6
Start removing pavement on north side of Main St July 6
Sidewalk repairs (Est) July 25
Paving north side of Main St starts August 8
Move traffic control to south side of Main St August 11
Start removing asphalt, south side August 12
Paving south side starts August 31
Landscape rock & cleanup Sept 5
Construction complete, demobilize Sept 12 - 15