Mainstreet Construction Timeline

After visiting with them and showing them the radar, the construction crew was a little worried about the incoming storms, but like all of us, there was nothing they could do. We laughed, thinking they had just built a big wadding pond. I asked about the timeline, and Chuck Williams from KLJ sent me the following best estimate :

Construction mobilization July 5

Traffic control July 5-6

Construction begins July 6

Close north side of Main St July 6

Start removing pavement on north side of Main St July 6

Sidewalk repairs (Est) July 25

Paving north side of Main St starts August 8

Move traffic control to south side of Main St August 11

Start removing asphalt, south side August 12

Paving south side starts August 31

Landscape rock & cleanup Sept 5

Construction complete, demobilize Sept 12 - 15